Earthship construction: Day 13

Nicaragua real estate - Earthship community

The day was rainy but spirits were high. Luckily down here in Nicaragua the rain is soft and warm. Presently half of the house is harvesting water into the east cistern when it rains. This means that the oxcarts may not have to haul water for the construction of the project anymore.

Part of the goal for the remaining American team is to hand off to the Nicaraguan crew the techniques for building and Earthship. The intention is to train the local crew to be proficient in this unusual type of construction as they will be the ones building the remaining homes in the community.

Today the Nicaraguan crew plastered the bedroom dome and laid the bottle bricks. Justin worked on establishing the remaining interior arches which hold up the bond beam for the north side of the wood trusses while Demain and Ted built the forework for a portion of the bond beam on the exterior arched wall.

During lunch the sky let loose with a deluge of water making the building a slippery and muddy mess.

It certainly didn’t stop progress on the building though.

The remaining bottle formwork was completed for the systems room, more bottle work on the south wall was done and the whole site received a thorough internal cleanup as the rain has a tendency to send people inside looking for things to do in the dry.

Ladders are at a premium so the crew has become creative in building quick scaffolding to access the areas up high. The formwork on the south side is ready for concrete.

The structure is close to being built and it is now easy to imagine the proportion and location of the spaces. Two more days for the three amigos from Taos. Time has passed by too quickly and San Juan del Sur has been a beautiful and friendly temporary home.